NEW QUESTION 32
What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the system conversion?
- A. SAP code inspector
- B. Simplification item check (Si-check)
- C. Software provisioning manager
- D. Software update manager with database migration option
Answer: B
NEW QUESTION 33
How many change projects can be active at a time?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: B
NEW QUESTION 34
Which of the following is part of the explorer phase in the "new implementation of SAP S/4HANA cloud" transition path?
- A. Simplification and custom code impact analysis
- B. Solution validation and delta design
- C. Fit-to-standard
- D. Setup and enablement
Answer: B
NEW QUESTION 35
What tool do you use to configure an SAP Business Suite on-premise solution?
Please choose the correct answer.
Response:
- A. SAP Implementation Guide
- B. Configuration Composer
- C. ABAP Workbench
- D. Expert Configuration
Answer: A
NEW QUESTION 36
Which of the following will help you avoid modification of standard functionality in SAP S/4HANA Cloud, Single Tenant Edit on?
There are 3 correct answers to this question.
Response:
- A. Contract restrictions in SAP HANA Enterprise Cloud and SAP S/4HANA Cloud, Single Tenant Edition
- B. SAP Code Inspector
- C. The Side-by-Side Extensibility Option (such as SAP Cloud Platform)
- D. A developer key
- E. The 5 Golden Rules
Answer: A,C,E
NEW QUESTION 37
What is the minimum number of quality gates mandated by the SAP Activate methodology?
Please choose the correct answer.
Response:
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 38
Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase?
Please choose the correct answer.
Response:
- A. Conduct Delta Design workshops
- B. Prioritize initial backlog
- C. a. Conduct Solution Validation workshops
- D. Conduct Delta Design workshops
- E. Conduct Delta Design workshops
- F. a. Set reference value
- G. Conduct Delta Design workshops
- H. Conduct Solution Validation workshops
- I. a. Conduct Solution Validation workshops
- J. Set reference value
- K. a. Set reference value
- L. Prioritize initial backlog
- M. Conduct Solution Validation workshops
- N. Set reference value
- O. Prioritize initial backlog
- P. Prioritize initial backlog
Answer: D
NEW QUESTION 39
Which of the following are the pillars of SAP Activate? There are 3 correct answers to this question.
- A. SAP Launch Methodology
- B. SAP Activate Methodology
- C. SAP ASAP Methodology
- D. SAP Best Practices
- E. Guided Configuration
Answer: B,D,E
NEW QUESTION 40
When is provisioning of the production system requested?
- A. Immediately after receiving the active quality system
- B. After completing configuration of the business processes in thequality system
- C. After the starter system is decommissioned
- D. Immediately after receive the inactive quality system (Preset phase)
Answer: A
NEW QUESTION 41
How would you describe the Realize phase in the "New Implementation of SAP S/4HANA" transition path?
Please choose the correct answer.
Response:
- A. Configuration copy
- B. Configure and adjust custom code
- C. Configure and develop
- D. Configure
Answer: D
NEW QUESTION 42
In which phase do you create an ordered list of everything that is known to be needed in the product"?
Please choose the correct answer.
Response:
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: D
NEW QUESTION 43
In which phase you execute the User Acceptance Test?
Please choose the correct answer.
Response:
- A. Final Preparation
- B. Build and Test
- C. Deploy
- D. Realize
Answer: D
NEW QUESTION 44
What is the purpose of afirm-up sprint?
Please choose the correct answer.
Response:
- A. To revise a release plan and sprint plan
- B. To perform sprint testing
- C. To run end-to-end integration test
- D. To demonstrate functionality from previous sprint
Answer: B
NEW QUESTION 45
Why do you use the Implementation Portal for SAP S/4HANA Cloud?
- A. To use the guided workflow to integrate SAP Cloud solutions.
- B. To monitor the progress of implementation tasks in real time.
- C. To use asan input for Fit-to-Standard workshops that helps the team understand areas to spend more time on during workshops.
- D. To manage implementation tasks based on SAP Activate Methodology that are automatically generated and adapted to thecustomer's scope.
Answer: B,D
NEW QUESTION 46
Who determines the priority of user stories in the backlog of an Agile project?
Please choose the correct answer.
Response:
- A. SCRUM Master
- B. Project Manager
- C. Project Team
- D. Product Owner
Answer: D
NEW QUESTION 47
Which Value Chains does SAP Solution Manager 7.2 deliver?
There are 3 correct answers to this question.
Response:
- A. Hire-to-Retire
- B. Requirements-to-Deploy
- C. Request-to-Fulfill
- D. Cash-to-Order
- E. Detect-to-Correct
Answer: B,C,E
NEW QUESTION 48
What are some of the intelligent technologies that enable end-to-end automation?
- A. Predictive Analytics
- B. Conversational AI
- C. Fundamental Simplification
- D. Embedded Analytics
- E. Machine Learning
Answer: A,B,E
NEW QUESTION 49
What structure level do you see when you access the Roadmap Viewer and chose work stream navigation?
Please choose the correct answer.
Response:
- A. Deliverable
- B. Task
- C. Scenario
- D. Scope Item
Answer: A
NEW QUESTION 50
What are the responsibilities of the Project Team on level 4 in the picture below?
There are 2 correct answers to this question.
Response:
- A. Set business priorities, goals and objectives
- B. Set Project policy, standards and oversight
- C. Identify and resolve issues and risks
- D. Perform status reporting and communication
Answer: C,D
NEW QUESTION 51
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?
Please choose the correct answer.
Response:
- A. Explore
- B. Deploy
- C. Prepare
- D. Realize
Answer: A
NEW QUESTION 52
Which of the following tasks are part of the Production support after the Go Live keydeliverable?
There are 2 correct answers to this question.
Response:
- A. Set up the Operations Control Center
- B. Resolve issues identified during the Hyper Care period
- C. Provide further training to customer end users
- D. Perform a Technical systems test
Answer: B,C
NEW QUESTION 53
Which of the following are not phases of the SAP Activate methodology? There are 2 correct answers to this question.
- A. Prepare
- B. Realize
- C. Go-Live & Support
- D. Preparation
Answer: C,D
NEW QUESTION 54
What are some responsibilities of the Configuration Expert project team role in an SAP S/4HANA Cloud implementation?
- A. Serves as the central contact for SAP
- B. Prepares and leads the Fit-to-Standard analysis process
- C. Manages interactionswith the SAP Service Center
- D. Resolution of business process issues
Answer: B,D