NEW QUESTION # 17
You define new SAP Extended Warehouse Management (SAP EWM) delivery document types for inbound delivery processes. Which additional customizing step is required in SAP EWM?
- A. Define a document category for the inbound process.
- B. Create a new system profile for the field control.
- C. Map an SAP ERP document type to the delivery document type.
- D. Define a delivery item type for the inbound process.
Answer: C
NEW QUESTION # 18
Which of the following are storage type roles? Note: There are 3 correct answers to this question.
- A. Production Supply
- B. Conveyor System
- C. Identification Point
- D. Work Center in Staging Area Group
- E. Deconsolidation
Answer: A,C,D
NEW QUESTION # 19
You have maintained several process types that should all use the same storage type search sequence for putaway. You want to minimize customizing efforts and create only one entry for these process types. What can you use to achieve this goal?
- A. Activity assigned to process type
- B. Putaway control indicator
- C. Process type group
- D. Storage process
Answer: C
NEW QUESTION # 20
Which field in the warehouse process type is used to determine warehouse order creation rules?
- A. Priority
- B. Destination storage type
- C. Storage process
- D. Activity
Answer: D
NEW QUESTION # 21
To which of the following objects can you assign external process steps? Note: There are 2 correct answers to this question.
- A. Work center
- B. Packaging specification
- C. Delivery item type
- D. Handling unit type
Answer: A,D
NEW QUESTION # 22
Which assignment do you make to create external process steps in process-oriented storage control?
- A. External process step to a storage process
- B. External process step to a warehouse process type
- C. External process step to a work center
- D. External process step to an SAP internal process step
Answer: D
NEW QUESTION # 23
An exception code can be triggered by the system or entered by a user. What must you assign to a customer-specific exception code?
- A. An internal exception code
- B. A workflow as follow-on action
- C. A business context
- D. A process step
Answer: A
NEW QUESTION # 24
Which of the following actions can you perform from the shipping cockpit? Note: There are 2 correct answers to this question.
- A. Create waves.
- B. Assign outbound delivery orders and inbound deliveries to transportation units.
- C. Create and check in transportation units.
- D. Post goods receipts.
Answer: A,C
NEW QUESTION # 25
What are the advantages of using a mobile device during physical inventory? Note: There are 2 correct answers to this question.
- A. You can use collective counting for bulk storage.
- B. It is optional to block bin.
- C. The stock is immediately corrected in SAP ERP.
- D. There is a special SAP Fiori app available.
Answer: A,C
NEW QUESTION # 26
What determines the source bin of a product in an inbound delivery? Note: There are 2 correct answers to this question.
- A. Warehouse task
- B. Warehouse process type
- C. Staging area and door determination
- D. Storage process
Answer: B,C
NEW QUESTION # 27
With SAP S/4HANA embedded EWM or EWM 9.5, you can skip certain document categories. Which document category combination is still mandatory?
- A. An outbound delivery order and an outbound delivery
- B. A production material request and a stock transfer
- C. An outbound delivery request and an outbound delivery order
- D. An outbound delivery request and an outbound delivery
Answer: A
NEW QUESTION # 28
How are waves created? Note: There are 2 correct answers to this question.
- A. Automatically when a warehouse task is created
- B. Manually during planning in the shipping cockpit
- C. Automatically when a production material request is created
- D. Automatically when an outbound delivery order is created
Answer: B,D
NEW QUESTION # 29
What is the specific characteristic of the early capacity check?
- A. It is based on capacities of bin types.
- B. It only happens during the warehouse task creation.
- C. It is only done during the actual picking process.
- D. It is only available when working with mobile devices.
Answer: B
NEW QUESTION # 30
What do you use to control what is displayed on the mobile device? Note: There are 2 correct answers to this question.
- A. User profile
- B. Presentation profile
- C. Queue type
- D. Personalization profile
Answer: B,D
NEW QUESTION # 31
What is required to perform explicit counting using the Quality Inspection Engine? Note: There are 2 correct answers to this question.
- A. Sampling procedure
- B. QM integration
- C. Work center
- D. Inspection rule
Answer: C,D
NEW QUESTION # 32
How can you determine the labor activities to calculate the planned duration for activities in the warehouse? Note: There are 2 correct answers to this question.
- A. Using a decision service in BRFplus
- B. Using a work step sequence
- C. Directly
- D. As a standard step
Answer: A,C
NEW QUESTION # 33
Which of the following are product warehouse tasks during putaway with process-oriented storage control?
- A. All process steps
- B. The first and final process step
- C. The final process step
- D. The first process step
Answer: D
NEW QUESTION # 34
How can you configure the storage of products in a temperature-controlled area of a warehouse? Note: There are 3 correct answers to this question.
- A. Configure a material staging area
- B. Create a new storage bin type
- C. Create a new putaway control indicator
- D. Create a new storage type
- E. Configure a storage type search sequence
Answer: C,D,E
NEW QUESTION # 35
Which objects in the SAP Extended Warehouse Management (SAP EWM) application are used to map an SAP ERP warehouse to an SAP EWM warehouse? Note: There are 2 correct answers to this question.
- A. Business system
- B. Storage location
- C. Warehouse number
- D. Plant
Answer: A,C
NEW QUESTION # 36
In process-oriented storage control, what can you use rule-based determination for?
- A. To determine the warehouse process type
- B. To determine the destination storage bin
- C. To determine the processing time
- D. To determine the HU type group
Answer: B
NEW QUESTION # 37
How can you determine the labor activities to calculate the planned duration for activities in the warehouse?
Note: There are 2 correct answers to this question.
- A. Using a decision service in BRFplus
- B. Using a work step sequence
- C. Directly
- D. As a standard step
Answer: A,C