NEW QUESTION # 86
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.

  • A. shortest; shortest
  • B. longest; longest
  • C. shortest; longest
  • D. longest; shortest

Answer: D


NEW QUESTION # 87
One of the main outputs of the _____ process are the issue logs.

  • A. Planning stakeholder management
  • B. Identifying stakeholders
  • C. Controlling stakeholder engagement
  • D. Managing stakeholder engagement

Answer: D


NEW QUESTION # 88
The bottom four needs in Maslow's structure are referred to as _____ needs.

  • A. safety
  • B. growth
  • C. self-actualization
  • D. deficiency

Answer: C


NEW QUESTION # 89
According to Thamhain and Wilemon, _____ is the legitimate hierarchical right to issue orders.

  • A. expertise
  • B. achievement
  • C. self-actualization
  • D. authority

Answer: D


NEW QUESTION # 90
Recognizing an employee as the "Star Performer of the Month" would be satisfying the _____ need of the Maslow's hierarchy of needs.

  • A. physiological
  • B. safety
  • C. esteem
  • D. self-actualization

Answer: C


NEW QUESTION # 91
Which of the following is true of the project life cycle?

  • A. more resources are usually needed during the initial phases of a project than during the middle or final phases
  • B. in the early phases of a project life cycle, resource needs are usually lowest
  • C. in the later phases of the project life cycle, the level of uncertainty is usually the highest
  • D. it is much more expensive to make major changes to a project during the earlier phases than the latter phases

Answer: D


NEW QUESTION # 92
_____ involves doing whatever you can to make sure the positive risk happens.

  • A. Risk enhancement
  • B. Risk exploitation
  • C. Risk sharing
  • D. Risk acceptance

Answer: B


NEW QUESTION # 93
A preliminary or rough cost estimate is developed in the _____ phase of the project life cycle, and an overview of the work involved is created.

  • A. concept
  • B. implementation
  • C. acquisition
  • D. close-out

Answer: A


NEW QUESTION # 94
A work package must always represent less than 80 hours of work.

  • A. False
  • B. True

Answer: A


NEW QUESTION # 95
One of the main outputs of the _____ process is a cost baseline.

  • A. cost budgeting
  • B. cost estimating
  • C. cost controlling
  • D. cost planning

Answer: A


NEW QUESTION # 96
The process of controlling costs primarily involves:

  • A. deining the policies for project costs
  • B. managing changes to the project budget
  • C. deining a basis for estimates
  • D. finalizing the procedures for project costs

Answer: B


NEW QUESTION # 97
_____ addresses how well a product or service performs the customer's intended use.

  • A. Maintainability
  • B. Reliability
  • C. Functionality
  • D. Performance

Answer: D


NEW QUESTION # 98
Which of the following provides certifications as a Project Management Professional?

  • A. PMC
  • B. PMP
  • C. PMS
  • D. PMI

Answer: C


NEW QUESTION # 99
_____ involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance.

  • A. Deining the budget
  • B. Controlling costs
  • C. Finalizing policies for project costs
  • D. Estimating costs

Answer: A


NEW QUESTION # 100
_____ addresses the ease of performing maintenance on a product.

  • A. Reliability
  • B. Functionality
  • C. Maintainability
  • D. Performance

Answer: C


NEW QUESTION # 101
In which of the following contracts does the buyer pay the supplier for allowable performance costs along with a predeined percentage based on total costs?

  • A. FPIF
  • B. CPPC
  • C. CPIF
  • D. CPAF

Answer: B


NEW QUESTION # 102
A _____ is a standard of measurement in quality management.

  • A. milestone
  • B. matrix
  • C. merge
  • D. metric

Answer: D


NEW QUESTION # 103
The output of the _____ process is a communications management plan.

  • A. managing communications
  • B. controlling communications
  • C. planning communications
  • D. reporting performance

Answer: C


NEW QUESTION # 104
When an organization needs a new direction, the _____ leadership style is appropriate.

  • A. commanding
  • B. democratic
  • C. visionary
  • D. pacesetting

Answer: C


NEW QUESTION # 105
Identifying the project sponsor is a pre-initiation task.

  • A. True
  • B. False

Answer: A


NEW QUESTION # 106
NPV analysis is a method for making equal comparisons between cash flows for multi-year projects.

  • A. True
  • B. False

Answer: A


NEW QUESTION # 107
"A shortage of qualified personnel is one of the main reasons that companies outsource. A project may require experts in a particular field for several months and planning for this procurement ensures that the needed services will be available for the project." Which of the following benefits does this characteristic of outsourcing provide an organization?

  • A. Increases control over all aspects of projects that suppliers carry out
  • B. Reduces dependency on suppliers
  • C. Provides access to specific skills
  • D. Reduces focus on its core business

Answer: C


NEW QUESTION # 108
A(n) _____ is an overall model for thinking about things as sets of interacting components working within an environment to fulfill some purpose.

  • A. preventive actions
  • B. finish-to-start
  • C. systems philosophy
  • D. scope statement

Answer: C


NEW QUESTION # 109
A risk-seeking person prefers outcomes that are more uncertain and is often willing to pay a penalty to take risks.

  • A. True
  • B. False

Answer: A


NEW QUESTION # 110
......