NEW QUESTION # 40
Which business process activities create a Financial Accounting (FI) document?
Note: There are 3 correct answers to this question.

  • A. Transfer stock to another company code
  • B. Post goods issue to a production order
  • C. Execute a depreciation run
  • D. Create a sales order
  • E. Transfer stock from storage location to storage location

Answer: A


NEW QUESTION # 41
You've been tasked with converting SAP Fiori Tile groups to SAP Fiori Spaces.
Which of the following assignments should be made?

  • A. Assign Sections to Spaces
  • B. Assign Spaces to Pages
  • C. Assign Pages to Spaces
  • D. Assign Tiles to Pages

Answer: C


NEW QUESTION # 42
Which action updates the costing-based profitability analysis?

  • A. Post the customer's payment
  • B. Post goods issue
  • C. Create the outbound delivery
  • D. Save the billing document

Answer: D


NEW QUESTION # 43
Which of the following are business partner categories in SAP S/4HANA?
Note: There are 3 correct answers to this question.

  • A. Group
  • B. Individual
  • C. Corporation
  • D. Person
  • E. Organization

Answer: A,D,E


NEW QUESTION # 44
Which controlling object is always a statistical object?

  • A. Cost center
  • B. Profit center
  • C. Internal order
  • D. Profitability segment

Answer: B


NEW QUESTION # 45
Which documents does SAP Transportation Management support when planning transportation with SAP S/4HANA? Note: There are 3 correct answers to this question.

  • A. Stock transport orders
  • B. Material documents
  • C. Transfer orders
  • D. Inbound deliveries
  • E. Returns

Answer: A,D,E


NEW QUESTION # 46
What is the result of converting a planned order? Note: There are 2 correct answers to this question.

  • A. A purchase order
  • B. A planned independent requirement
  • C. A production order
  • D. A purchase requisition

Answer: C,D


NEW QUESTION # 47
What action assigns actual costs to a project?

  • A. Material availability check
  • B. Saving a purchase order
  • C. Releasing a project budget
  • D. Material withdrawal from stock

Answer: C


NEW QUESTION # 48
Which of the following is a permitted hierarchical structure for Management Accounting in the SAP S/4HANA enterprise structure?

  • A. A controlling area is assigned to a plant.
  • B. A controlling area is assigned to an operating concern.
  • C. An operating concern is assigned to a controlling area.
  • D. An operating concern is assigned to a company code.

Answer: B


NEW QUESTION # 49
What are the benefits of using a business partner in SAP S/4HANA?
Note: There are 2 correct answers to this question.

  • A. Vendors are managed separately from customers.
  • B. General data is unique to each assigned role.
  • C. Redundant data is reduced.
  • D. Data architecture is harmonized.

Answer: C,D


NEW QUESTION # 50
You have found a new source of supply for a material.
When maintaining the Business Partner information for the Supplier role, which organizational unit should be extended?

  • A. Plant
  • B. Purchasing Group
  • C. Purchasing Organization
  • D. Company Code

Answer: C


NEW QUESTION # 51
In a warehouse, what represents the physical location where the goods are stored?

  • A. Storage section
  • B. Pallet
  • C. Storage location
  • D. Storage bin

Answer: D


NEW QUESTION # 52
Which master records are directly assigned to a company code?
Note: There are 2 correct answers to this question.

  • A. Fixed asset
  • B. Cost center
  • C. Activity type
  • D. Material

Answer: A,B


NEW QUESTION # 53
Which backorder processing (BOP) strategy has first processing priority and is used to release confirmed stock to prioritize other orders to plan future stock needs?

  • A. Fill
  • B. Win
  • C. Gain
  • D. Lose

Answer: B


NEW QUESTION # 54
When is backorder processing considered?

  • A. When order quantity is not fully confirmed
  • B. When advanced available-to-promise is unavailable
  • C. When planning transportation
  • D. When goods issue is performed

Answer: A


NEW QUESTION # 55
During the production order process, what steps can be executed via background processing?
Note: There are 3 correct answers to this question.

  • A. Order confirmation
  • B. Order creation
  • C. Order settlement
  • D. Order release
  • E. WIP determination

Answer: C


NEW QUESTION # 56
Which object is created to report on market characteristics, such as customer, product, and region?

  • A. Segment
  • B. Profit center
  • C. Profitability segment
  • D. Sales organization

Answer: C


NEW QUESTION # 57
What does a work center control?
Note: There are 2 correct answers to this question.

  • A. Calculation of costs of work performed
  • B. Availability of capacity
  • C. Valuation of bill of material components
  • D. Release of production orders

Answer: A,B


NEW QUESTION # 58
Which SAP Suite line-of-business solution can be used to enhance the procurement of external services?

  • A. SAP Ariba
  • B. SAP Concur Travel and Expense
  • C. SAP Fieldglass
  • D. SAP SuccessFactors

Answer: C


NEW QUESTION # 59
Which controlling objects can be settled by a settlement rule in SAP S/4HANA? Note: There are 3 correct answers to this question.

  • A. Production order
  • B. WBS element
  • C. Sales order
  • D. Profit center
  • E. Maintenance order

Answer: A,B,E


NEW QUESTION # 60
Why would you enter your working hours using Cross-Application Time Sheet (CATS)?
Note: There are 3 correct answers to this question.

  • A. To confirm activities
  • B. To maintain absence
  • C. To request absence
  • D. To record overtime
  • E. To plan time

Answer: A


NEW QUESTION # 61
Which of the following applies to Sales and Distribution enterprise structures?
Note: There are 3 correct answers to this question.

  • A. A division can only be assigned to one sales organization.
  • B. A sales organization can be assigned to more than one company code.
  • C. A division can be assigned to more than one sales organization.
  • D. A sales organization can only be assigned to one company code.
  • E. A distribution channel can be assigned to many sales organizations.

Answer: C,D,E


NEW QUESTION # 62
What occurs when a maintenance technician changes the status of an order to technically completed? Note: There are 3 correct answers to this question.

  • A. The orders settlement rule is executed.
  • B. A time entry is posted for the maintenance technician.
  • C. Incoming invoices for the order can be processed.
  • D. Open purchase requisitions are marked for deletion.
  • E. Reserved materials are released from the reservation.

Answer: A


NEW QUESTION # 63
Which of the following can be maintained in a maintenance notification?
Note: There are 3 correct answers to this question.

  • A. Cause of damage
  • B. Materials planning
  • C. Tasks
  • D. Equipment
  • E. Capacity requirements

Answer: A,C,D