NEW QUESTION 33
Consider the following list of statements about audits and management reviews:
I. Audits are usually more effective than management reviews at finding defects
II. Audits and management reviews have the same main goals, the only difference is related to the roles and level of formality
III. A typical outcome of an audit includes observations and recommendations, corrective actions and a pass/fail assessment
IV. An audit is not the appropriate mechanism to use at the code review in order to detect defects prior to dynamic testing
Which of the following statements is true?
K2 1 credit

  • A. I, III and IV are true; II. is false;
  • B. III. and IV. are true; I and II are false;
  • C. I. and III. are true; II. and IV. are false;
  • D. II. and III are true; I. and IV. are false;

Answer: B

 

NEW QUESTION 34
Test Management
Which one of the following metrics to be produced needs traceability between the test cases and each item in a proper test basis?
Number of correct responses: 1
K2 1 credit

  • A. Trends in the lag time from defect reporting to resolution
  • B. Mean time between failures for the system
  • C. Requirements coverage
  • D. Cumulative number of reported defects versus cumulative number of resolved defects

Answer: C

 

NEW QUESTION 35
Test Management
Consider an agile team adopting Extreme Programming (XP) with five developers and one tester without any coding experience.
To which of the following activities would you expect the tester will contribute most?
Number of correct responses: 1
K2 1 credit

  • A. Executing unit tests
  • B. Supporting the customer in the execution of acceptance testing
  • C. Planning and executing tests during the integration test phase to detect interface defects
  • D. Developing unit tests

Answer: B

 

NEW QUESTION 36
Test Tools and Automation
Assume you are a Test Manager involved in system testing of a CRM application for a Pay-TV company.
Currently the application is able to support a proper number of users assuring the required responsiveness.
Since the business is expected to grow, you have been asked to evaluate the ability of the application to grow to support more users while maintaining the same responsiveness.
Which of the following tools would you expect to be the most useful at performing this evaluation?
Number of correct responses: 1
K2 1 credit

  • A. Coverage tools
  • B. Test management tools
  • C. Static analysis tools
  • D. Performance tools

Answer: D

 

NEW QUESTION 37
Test Management
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:
I. Availability of re-usable test systems and documentation from previous, similar projects II. Unexpected timing of components arrival
III. Stability of the integration test team (no turnover)
IV. Many and geographically distributed sub-teams
Which of the following statements is true?

  • A. III and IV usually favor the accuracy of the estimation effort
  • B. II and III usually favor the accuracy of the estimation effort
  • C. III and IV can negatively affect the estimation
  • D. II and IV can negatively affect the estimation
  • E. I and II can negatively affect the estimation III and IV usually favor the accuracy of the estimation effort
  • F. II and III can negatively affect the estimation
  • G. I and II usually favor the accuracy of the estimation effort

Answer: A

 

NEW QUESTION 38
Which of the following statements about management of product quality risks in mature organizations with respect to the lifecycle, is true?
K2 1 credit

  • A. Mature organizations are aware that risk management of product quality risks only occurs during testing
  • B. Mature organizations are aware that the contribution of testing to analysis of product quality risks is very important. The analysis should occur throughout the entire lifecycle
  • C. Mature organizations address product quality risks associated to non-functional characteristics only during the system test phase
  • D. Mature organizations don't waste time identifying the sources of risks. They only focus on identifying product quality risks

Answer: B

 

NEW QUESTION 39
Assume that the following test cases have been executed at the end of the first week of test execution: TC-001, TC-002 and TC-007. All these tests are 'passes'.

What is the MINIMUM number of the remaining test cases that must be successfully executed to fulfill the EX1 exit criteria?
K3 2 credits

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: D

 

NEW QUESTION 40
Assume you are a Test Manager involved in system testing of a CRM application for a Pay-TV company. Currently the application is able to support a proper number of users assuring the required responsiveness. Since the business is expected to grow, you have been asked to evaluate the ability of the application to grow to support more users while maintaining the same responsiveness.
Which of the following tools would you expect to be the most useful at performing this evaluation?
K2 1 credit

  • A. Coverage tools
  • B. Test management tools
  • C. Static analysis tools
  • D. Performance tools

Answer: D

Explanation:
Topic 7, People Skills - Team Composition

 

NEW QUESTION 41
Consider the following test strategies:
I. Consultative test strategy
II. Reactive test strategy
III. Analytical test strategy
IV. Process-compliant test strategy
Consider also the following examples of test activities:
1.Prioritize the test cases, based on the results of a FMEA analysis, to ensure early coverage of the most important areas and discovery of the most important defects during test execution
2.Execute usability testing driven by the guidance of a sample of users (external to the test team)
3.Perform exploratory testing sessions throughout the system test phase
4.On an Agile project, execute tests that cover the test conditions identified for each user story of a feature planned for an iteration
Which of the following correctly matches each test strategy with an appropriate example?
K2 1 credit

  • A. I-2; II-3; III-1; IV-4
  • B. I-1; II-2; III-3; IV-4
  • C. I-3; II-2; III-1; IV-4
  • D. I-2; II-3; III-4; IV-1

Answer: A

 

NEW QUESTION 42
Defect Management
Consider a defect report and assume that a part of its lifecycle includes the following states:
New: Is the initial state
Working: Means that the developers are addressing the defect in order to produce a fix for the defect Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect
Closed: is the final state
Which of the following answers represents an invalid sequence of states that can't lead the bug report to the "Closed" state?

  • A. New, Working, Verification, Closed
  • B. New, Working, Verification, Working, Clarification, Working, Closed
  • C. New, Working, Verification, Working, Clarification, Working, Verification, Closed
  • D. New, Working, Clarification, Working, Verification, Closed

Answer: B

 

NEW QUESTION 43
Test Management
Assume you are managing the system testing phase of a project.
The system test execution period is scheduled to twenty weeks.
All tests are manual tests. You are following a risk-driven test approach.
During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests.
Which of the following would you expect to be the best way to respond to this situation?

  • A. Prioritize executing the tests for the highest product risks and track these risks
  • B. Remove testers from your test team, so that they can be assigned to other projects
  • C. No action is needed, test as much as possible in the remaining time period
  • D. Automate all remaining tests

Answer: A

Explanation:
Section: Test Management

 

NEW QUESTION 44
You are working on a project to develop an authentication system for an e-commerce website. This system provides two features: Registration and authentication. Two different development teams develop these two features.
There is a high likelihood that the delivery of the authentication feature to the test team will be three weeks later. To complete the registration the user must provide the following registration inputs: Name, surname, birth date, fiscal code and he/she can select a username and a password.
A registered user can be a special user or a normal user. To be identified as a special user, he/she must also provide, during the registration process, a voucher possibly received from the IT department.
Access is granted only if a user is registered and the password is correct: In all other cases access is denied. If the registered user is a special user and the password is wrong, a special warning is shown on the system console.
You are currently performing a quality risk analysis using FMEA.
Based only on the given information, which of the following is NOT a product risk that could be identified during the quality risk analysis?
K4 3 credits

  • A. The late delivery of the authentication feature to the test team causes delays in the start of test execution and this could result in a shorter test period
  • B. The authentication system grants access to a special user with a wrong password
  • C. The authentication system denies access for a special user with a wrong password, but doesn't display a special warning on the system console
  • D. The authentication system grants access to a normal user with a wrong password

Answer: A

 

NEW QUESTION 45
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:
I. Availability of re-usable test systems and documentation from previous, similar projects
II. Unexpected timing of components arrival
III. Stability of the integration test team (no turnover)
IV. Many and geographically distributed sub-teams Which of the following statements is true?
K2 1 credit

  • A. and IV. usually favor the accuracy of the estimation effort
  • B. II. and III. can negatively affect the estimation
  • C. and II. usually favor the accuracy of the estimation effort
  • D. III. and IV. can negatively affect the estimation
  • E. II. and IV. can negatively affect the estimation
  • F. I. and II. can negatively affect the estimation III. and IV. usually favor the accuracy of the estimation effort
  • G. and III. usually favor the accuracy of the estimation effort

Answer: A

 

NEW QUESTION 46
Which of the following would you expect to be most likely an example of a demotivating factor for testers?
K2 1 credit

  • A. The same regressions tests are manually executed by the same testers, for every product release, without regression test tools
  • B. The testers' recommendations to improve the system or its testability are adopted by the development team
  • C. The management asks the testers to be kept informed about the intensity, quality and results of testing
  • D. The testers are assessed on whether and how often they detect important and critical failures
  • E. Test quality is measured by counting the number of customer/user reported problems.

Answer: A,E

 

NEW QUESTION 47
The following is the unique "critical" quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user Test analysis for system testing has just begun and the following test conditions have been identified:
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario.
Which of the following is a positive logical test that is complete and correct, and covers the REQ-SEL-4 requirement?
Number of correct responses: 1
K3 2 credits

  • A. Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of bottles" message is displayed
  • B. Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are displayed
  • C. Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are displayed
  • D. Select a 6-bottles package, then try to insert 7 bottles

Answer: A

 

NEW QUESTION 48
Which of the following statements about the TMMi test process improvement model is true?
K2 1 credit

  • A. In TMMi all the process areas at lower levels must be 75% complete by achieving specific and generic goals in order to claim the higher level
  • B. At TMMi level 1 testing is chaotic without a defined process, and it is often seen as the same as debugging
  • C. TMMi provides an approach for test process improvement such as the IDEAL (Initiating, Diagnosing, Establishing, Acting and Learning) model
  • D. TMMi has a staged architecture for process improvement with seven maturity levels

Answer: B

 

NEW QUESTION 49
Test Tools and Automation
Assume you are the Test Manager in charge of independent testing for avionics applications.
You are in charge of testing for a project to implement three different CSCI (Computer Software Configuration Item):
- a BOOT-X CSCI that must be certified at level B of the DO-178B standard
- a DIAG-X CSCI that must be certified at level C of the DO-178B standard
- a DRIV-X CSCI that must be certified at level A of the DO-178B standard These are three different software modules written in C language to run on a specific hardware platform.
You have been asked to select a single code coverage tool to perform the mandatory code coverage measurements, in order to meet the structural coverage criteria prescribed by the DO-178B standard. This tool must be qualified as a verification tool under DO-178B.
Since there are significant budget constraints to purchase this tool, you are evaluating an open-source tool that is able to provide different types of code coverage. This tool meets perfectly your technical needs in terms of the programming language and the specific hardware platform (it supports also the specific C-compiler).
The source code of the tool is available.
Your team could easily customize the tool to meet the project needs. This tool is not qualified as a verification tool under the DO-178B.
Which of the following are the three main concerns related to that open-source tool selection?
Number of correct responses: 3
K4 3 credits (2 credits out of 3 credits correct, 1 credit point)

  • A. Does the tool support all the types of code coverage required from the three levels A, B, C of the DO-178B standard?
  • B. What are the costs to qualify the tool as a verification tool under the DO-178B?
  • C. Does the tool have a good general usability?
  • D. Is the installation procedure of the tool easy?
  • E. Does the tool require a system with more than 4GB of RAM memory?
  • F. Is the licensing scheme of the tool compatible with the confidentiality needs of the avionics company?

Answer: A,B,F

 

NEW QUESTION 50
Test Management
In the next two months some new features will be constantly added to new releases of a project you are working on as Test Manager.
You have identified as one of the main project risks, that the requirements specification will still be incomplete when your team starts the test design and implementation phase.
Some requirements will most likely be completed too late to allow a proper test preparation.
You and your test team have already worked on several similar past projects in the same organization.
Which one of the following options would you expect to be the most effective at mitigating this risk?

  • A. Even if there are only few details missing, escalate the risk to the project manager without preparing any tests
  • B. Make reasonable assumptions about the missing details and design lightweight tests that can be easily updated during test execution
  • C. Don't design any test until the test execution starts, then communicate that test execution is blocked due to incomplete requirements
  • D. Don't prepare any test and just run the regression test suite to check that the new features don't introduce regression

Answer: B

 

NEW QUESTION 51
Test Management
You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations.
At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested.
Which of the following statements is true in this context?

  • A. You should allocate all the effort for the system test phase only in the last iteration
  • B. The system test phase should start when all the requirements are frozen
  • C. You should allocate a large effort for system testing during the first three iterations
  • D. You should apply the same test strategy as used in a sequential life cycle model

Answer: C

 

NEW QUESTION 52
Reviews
You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews, (including their costs, benefits, and potential issues), the management finally decides to adopt formal reviews for future projects.
You have been given a budget that you have spent to provide training in the review process and to introduce the review process on a pilot project.
On that pilot project the introduction of reviews has been very positive in terms of positive involvement from all the participants. All the reviews applied to different documents have been very effective for their purposes (especially at revealing defects).
Which of the following answers describes an important success factor for the introduction of formal reviews which is missing in this scenario?

  • A. Definition and use of metrics to measure the ROI (Return On Investment)
  • B. Management support
  • C. Training in the review process
  • D. Participant support

Answer: A

 

NEW QUESTION 53
Test Management
Consider the following test strategies:
I. Consultative test strategy
II. Reactive test strategy
III. Analytical test strategy
IV. Process-compliant test strategy
Consider also the following examples of test activities:
1. Prioritize the test cases, based on the results of a FMEA analysis, to ensure early coverage of the most important areas and discovery of the most important defects during test execution
2. Execute usability testing driven by the guidance of a sample of users (external to the test team)
3. Perform exploratory testing sessions throughout the system test phase
4. On an Agile project, execute tests that cover the test conditions identified for each user story of a feature planned for an iteration
Which of the following correctly matches each test strategy with an appropriate example?

  • A. I-2; II-3; III-1; IV-4
  • B. I-1; II-2; III-3; IV-4
  • C. I-3; II-2; III-1; IV-4
  • D. I-2; II-3; III-4; IV-1

Answer: A

 

NEW QUESTION 54
......

Real Exam Questions & Answers - ISQI CTAL-TM_Syll2012 Dump is Ready: https://drive.google.com/open?id=15_Vzif8UFhLmmPWUXxxltZ2ITq_-wiRz