Latest [Apr 14, 2023] Scrum PSM-I Exam Practice Test To Gain Brilliante Result [Q18-Q36]

Share

Latest [Apr 14, 2023] Scrum PSM-I Exam Practice Test To Gain Brilliante Result

Take a Leap Forward in Your Career by Earning Scrum PSM-I


Career Opportunities

The professionals who have successfully passed the PSM I exam obtain the certificate that confirms their fundamental proficiency in the Scrum framework. With this sought-after certification, you can demonstrate to your potential employer that you have a solid understanding of Scrum as defined in the Scrum Guide and know how to apply it in Scrum Teams. Getting certified opens doors to multiple employment opportunities. Some of the job roles that you will be able to take up are as follows:

  • Team Leader
  • Agile Coach
  • Development Team Member
  • Project Manager
  • Business Analyst
  • Senior Project Manager
  • Software Engineering Manager

Additionally, the Scrum PSM I certification is highly advantageous in financial terms. According to PayScale, the average salary that the certificate holders can earn amounts to $92,567 per annum. Depending on a particular position and your level of experience, this sum can be much higher. For instance, holding the role of a Senior Project Manager can bring you around $110,000 per year, while the title of a Software Engineering Manager comes with $145,000 per annum.


Introduction

Scrum is a framework within which people can address complex adaptive problems, while productively and creatively delivering products of the highest possible value. A Professional Scrum Master is one such individual who knows how to manage the workflow effectively, create motivated and intelligent teams, and handle complex tasks while ensuring a collaborative project environment that promotes productivity and boost business worth.

A PSM certification endorses the holder's knowledge of Agile and Scrum practices/ exercises and makes them industry-ready. The PSM Certification is a well-known accreditation applicable in different sectors and industries and extremely valued within the scrum community.

 

NEW QUESTION 18
The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take? (Choose the best answer.)

  • A. Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.
  • B. Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.
  • C. Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.
  • D. Present the Product Owner with an ordered Product Backlog to use.
  • E. Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.

Answer: C

 

NEW QUESTION 19
Who is responsible for clearly expressing Product Backlog items?

  • A. The business analyst who represents the Product Owner in the Development Team.
  • B. The Product Owner.
  • C. The Scrum Master.
  • D. The Scrum Master, or the Scrum Master may have the Development Team do it.

Answer: B

 

NEW QUESTION 20
At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of "Done". What two things should happen with the undone Product Backlog item? (Choose the best two answers.)

  • A. Put it on the Product Backlog for the Product Owner to decide what to do with it.
  • B. If the stakeholders agree, the Product Owner can accept it and release it to the users.
  • C. Do not include the item in the Increment this Sprint.
  • D. Review the item, add the "Done" part of the estimate to the velocity and create a Story for the remaining work.

Answer: A,C

 

NEW QUESTION 21
Select two ways in which technical debt impacts transparency. (Choose two.)

  • A. It enhances transparency for the Product Owner as a Development Team is not allowed to do additional feature development in a Sprint as long as there is technical debt.
  • B. As development progresses and code is added, the system becomes more difficult to stabilize, which results in future work being slowed down in unpredictable ways.
  • C. It leads to false assumptions about the current state of the system, specifically of an Increment being releasable at the end of a Sprint.
  • D. When calculated and estimated, the total amount of technical debt shows exactly how long until the Product Owner can release the Increment.

Answer: B,C

Explanation:
Explanation/Reference:

 

NEW QUESTION 22
How is management external to the Scrum Team involved in the Daily Scrum?

  • A. The Product Owner represents their opinions.
  • B. The Scrum Master speaks ontheir behalf.
  • C. The Development Team self-manages and is the only management required at the Daily Scrum.
  • D. Management gives an update at the start of each Daily Scrum.

Answer: C

 

NEW QUESTION 23
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

  • A. Run the Daily Scrum.
  • B. Answer Question:s from the Development Team about items in the current Sprint.
  • C. Update management on what is being worked on.
  • D. Prioritize the Development Team's work on the Sprint Backlog.

Answer: B,C

 

NEW QUESTION 24
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:

  • A. The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done.
  • B. Add enough people to the Development Team for the deadline to be made.
  • C. The opportunity to inspect and adapt is lost. Opaqueness has replaced transparency. Predictability has dropped below zero. The produced software is not usable. As the rules of Scrum have not been respected, it is the Scrum Master's duty to assess whether repair is possible, or a restart with a more reliable team. If not, the Scrum Master should cancel the project.
  • D. The Development Team makes sure that all of the selected scope per Sprint is as "Done" as possible. The undone work is estimated and added to the Sprint Backlog of the next Sprint, so it doesn't mess up the Product Backlog.

Answer: D

 

NEW QUESTION 25
The Product Backlog is ordered by:

  • A. Size, where small items ale at the top and large items are at the bottom.
  • B. Items are randomly arranged.
  • C. The Product Owner with the most valuable items placed at the top.
  • D. Risk, where safer items are at the top, and riskier items are at the bottom.

Answer: C

 

NEW QUESTION 26
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

  • A. The Product Owner.
  • B. TheDevelopment Team.
  • C. The Scrum Team.
  • D. The Project Manager.

Answer: B

 

NEW QUESTION 27
Who is on the Scrum Team? (Choose all that apply.)

  • A. Scrum Master
  • B. None of the above
  • C. Product Owner
  • D. Project Manager
  • E. Development Team member

Answer: A,C,E

 

NEW QUESTION 28
A Development Team asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component.Without that component there won't be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master for help. What would be good advice to give the Product Owner?

  • A. Tell the Product Owner to re-order the Product Backlog so the work involving the external component can be planned in a separate sprint.
  • B. Tell the Product Owner that his primary concern isthe flow of value reflected in the ordering of the Product Backlog.
  • C. Tell the Product Owner that the Product Backlog should be ordered to maximize utilization of the Development Team.

Answer: B

 

NEW QUESTION 29
When should a Sprint Goal be created? (Choose the best answer.)

  • A. It should have been created in the previous Sprint during Product Backlog refinement.
  • B. A Sprint Goal is not mandatory in Scrum.
  • C. It must be established before Sprint Planning in order to begin planning.
  • D. During Sprint Planning.
  • E. At any time during the Sprint.

Answer: D

 

NEW QUESTION 30
The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)

  • A. Inform the Product Owner's functional manager.
  • B. Stop the Sprint, send the Product Owner to a course and restart.
  • C. Coach the Product Owner in the values of Scrum and incremental delivery.
  • D. Nominate a proxy Product Owner.
  • E. Bring up the problem in the Sprint Retrospective.

Answer: C,E

Explanation:
Explanation

 

NEW QUESTION 31
Which two of the following are true about the Scrum Master role? (Choose two.)

  • A. The Scrum Master is responsible for updating the Sprint Burndown.
  • B. The Scrum Master teaches the Development Team to keep the Scrum meetings to their time-box.
  • C. The Scrum Master assigns tasks to Development Team members when they need work.
  • D. At the Sprint Review, the Scrum Master identifies what has been "done" and what has not been "done".
  • E. The Scrum Master helps those outside the team interact with the Scrum Team.

Answer: B,E

 

NEW QUESTION 32
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

  • A. The Product Owner.
  • B. The Development Team.
  • C. The Scrum Team.
  • D. The Project Manager.

Answer: B

 

NEW QUESTION 33
Which technique is the best way the Scrum Master can ensure that the Development Team communicates effectively with the Product Owner?

  • A. Teach the Development Team to talk in terms of business needs and objectives.
  • B. Act as a go-between for them.
  • C. Monitor communications between them and facilitate directcollaboration.
  • D. Teach the Product Owner about the technologies employed during the Sprints.

Answer: C

 

NEW QUESTION 34
What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?

  • A. There are no such activities. The next Sprint starts immediately after the current Sprint.
  • B. Refine the Product Backlog.
  • C. Update the project plan with stakeholders.
  • D. Work with the Quality Assurance departments on the Increment of the current Sprint.

Answer: A

 

NEW QUESTION 35
Who determines how work is performed during the Sprint? (Choose the best answer.)

  • A. The Development Team.
  • B. Development Team managers.
  • C. The Scrum Master.
  • D. Architects.
  • E. Subject matter experts.

Answer: A

 

NEW QUESTION 36
......


Target Audience

The PSM I certification exam is intended for everyone who wants to gain the competencies and skills needed to implement Scrum within their organizations. The test is ideal for the professionals who are involved in software development with the help of the Scrum framework, including Scrum Masters, Managers, and Scrum Team Members.

 

Authentic Best resources for PSM-I Online Practice Exam: https://www.free4torrent.com/PSM-I-braindumps-torrent.html

Updates Up to 365 days On Developing PSM-I Braindumps: https://drive.google.com/open?id=1DRwUSoZkWEMJdrh0l9gWaM29mrNNYeYf